INFORMATION HANDOUT

CONTINENTAL BOULEVARD AREA
WATER SYSTEM IMPROVEMENTS
Merrimack Village District

 

Summary
The purpose of this project is to improve flow capacity from sources of supply in South Merrimack to meet demands in areas of North Merrimack. The project limits begin on Continental Boulevard just south of Industrial Drive and continue north on Continental Boulevard and Camp Sargent Road onto Amherst Road, to the intersection with Turkey Hill Road. The project has been extended to include approximately 3,700 LF on Turkey Hill Road, from Amherst Rd to Summit Road. The work includes:

• New 16" ductile iron water main.
• New water service connections.
• New hydrants

The project is funded by a $2.8M Bond approved by voters at the MVD March 2010 Annual Meeting.

Contact Information
General Info: Call Resident Engineer, Dave Foster with questions or comments at the field office trailer (603) 262-1618 or cell phone (603) 828 - 3519. The field office answering machine message will be updated regularly with the project status.

Complaints: Complete “Complaint Form” and submit to Contractor (with copy to Engineer). Forms are available on the MVD website listed below.

Project Contacts:

Contractor Engineer Owner
Haluch Water Contracting 399 Fuller Street, PO Box 510
Ludlow, MA 01056-0510
President (Field/Office):
      Tom Haluch (413) 583-3196
Underwood Engineers, Inc.
25 Vaughan Mall
Portsmouth, NH 03801
Resident Engineer (Field):
      Dave Foster (603) 828-3519
Project Engineer (Office):
      Tom Page (603) 436-6192
Merrimack Village District
2 Greens Pond Road
Merrimack, NH 03054-4259
Business Manager (Office):
      Jim McSweeney (603) 424-9241 x107
Administrative Manager:
      Jill Lavoie (603) 424-9241 x103
Email: jill.lavoie@mvdwater.org

Schedule (Tentative):

Service Connections on Camp Sargent, Amherst October 2010
Turkey Hill Road October, November 2010
Final Paving Spring 2011

Updates:

Project updates will be posted regularly on the this website.

Temporary signs will be placed in advance of construction activities. Please be aware of temporary changes in road surface conditions and traffic patterns. Every effort will be made to assure that reasonable access is maintained to residences and businesses within the work area. We apologize for any inconveniences and thank you for your cooperation.